Key Contacts
Court Finds Federal Government Not Immune from Liability for Interest Payment Under CERCLA
On April 26, 2023, the United States Court of Federal Claims ordered the federal government to reimburse Shell U.S.A. and several other oil companies for all cleanup costs, including interest, associated with the cleanup of aviation gas (“avgas”) at a site polluted during World War II efforts. Shell U.S.A., Inc. et al. v. United States, 2023 WL 3090659 at *10 (Fed. Cl. 2023). This was the third such case in which the oil companies were seeking contractual indemnification for costs pursuant to the Contract Settlement Act and the only issue of significance addressed by the Court was whether the Plaintiffs were entitled to recover statutory interest that they previously paid under the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”). Ultimately, the Court held that the plain reading of CERCLA includes interest as a “charge,” and the government was not immune from paying those costs. Id. at *8.
Read the full blog post.